Manufacturing Solutions is authorised by Davenport to rebuild and upgrade its machines. We were trained by Davenport engineers to undertake the work to their approved procedures. Manufacturing Solutions is the only company outside the USA to be approved for this work.

Since Jan 1st 1995 all machines rebuilt in the UK must comply with the CE legislation on guards and interlocks. We can supply CE compliant Davenport machines.

Rebuild Options
1.) Refurbished machine….Approx 6 weeks to complete
2.) Rebuilt and upgraded with HP head plus Logan start & stop clutches…. Approx 12 weeks to complete
3.) Rebuilt and upgraded to CE specification….Approx 15 weeks to complete
After a complete strip down, shot blasting and painting the 12 week rebuild program takes place.
Below a slide show on the process.
Stacks Image 264
Stacks Image 272
Stacks Image 274
Stacks Image 266
Stacks Image 278
Stacks Image 292
Stacks Image 294
Stacks Image 296
Stacks Image 298
Stacks Image 304
Stacks Image 308